   Free sample   Project management assignment construction of m6 motorway project

Project Management Assignment: Construction Of M6 Motorway Project

Question

Task: Brief
Balfour Beatty have successfully won the tender to construct the widening of the M6 motorway, Stafford. This includes the construction of a gabion retaining wall next to a field. Details of the proposed gabion retaining wall are given at the end of this project brief in the Appendix. This includes a cross section and construction details. These details are also given on Moodle. As a new project manager with Balfour Beatty, your senior manager has asked you to produce a detailed programme for the construction of a retaining wall between chainage 210 m and chainage 310 m. The wall is longer than this but you are only required to programme 100 metres.

Contract Arrangements
Due to accessibility problems, it will not be possible to enter into a contract with the client until 5th October 2020 (the NEC3 contract date). The site will only become available to actually start work on 19th October 2020 (the NEC3 access date). As this is an important part of the construction of the project, the retaining wall needs to be completed by 12th February 2021. This completion date is a very important date in the contract but the client can be persuaded to be flexible on it. The construction of the carriageway and footway are not included in this phase of the project.

Please note the following
The first operation is to set up the site compound which will house site offices, utilities, storage and welfare facilities in compliance with CDM regulations and then the site boundary fencing around the area of the proposed works. Your organisation has agreed with a local farmer that a nearby field with access from the B123 road may be used to set up the site compound. The field is adjacent to the site of the proposed gabion retaining wall.

The following should be taken into consideration for programming
Time constraints:

i. Assume a 5 day working week.
ii. Work must begin on a Monday
iii. The site boundary fencing around the area of the proposed works takes not less than one week.
iv. The entire site compound set up takes not less than two weeks.
v. Assume it takes a minimum of twenty days to excavate and another twenty days to backfill.
vi. Removal of the site boundary fencing and site compound takes 1 week.

Construction constraints:
i. The construction processes allow the footing to be constructed in only 5-metre-long bays with each bay taking not less than a day.
ii. Installation of the entire gabion retaining wall takes a minimum of thirty days.
iii. Placement of gabions on concrete footing may commence only after a minimum of 7 days, when the footing has obtained sufficient strength.
iv. It will be necessary to include engineered fill (e.g.6F2) for approximately 50 metres behind the gabion wall.
Use the video below as a guide on gabion basket installation:
https://www.youtube.com/watchv=pk6Y9syn0NU

Part 1

Based upon your knowledge of the Project Management and time management processes, perform the following tasks:
a) In no more than 300 words explain the following Project Management techniques;
• Work Breakdown Structure (WBS)
• Precedence Diagram Method
• Critical Path
• Fast tracking
• Crashing
• Float/slack

b) Draw a Work Breakdown Schedule (WBS) for the construction element of the project including setting up and clearance of site. The WBS must clearly show phases, deliverables, work packages and activities. The WBS should contain a sufficient number of activities to show the client that you understand the construction process and to aid in later programme control. You should include task IDs in the WBS.

c) Using the WBS, produced in ‘b’ above, produce a project schedule (manual Gantt chart (project programme) using MS Excel as taught in tutorials) and allocate reasonable estimates for durations and labour resources for the identified activities. Show days in day numbers and not dates.

d) Manually produce a precedence diagram for the construction phase of the project based upon your WBS and project schedule from tasks b) and c) above. Your diagram must be in standard notation and show your proposed critical path.

Answer

Part 1
Descriptions and definition of terms

1. Work Breakdown Structure (WBS)
This refers to a visual representation of the deliverables of the construction project. A work breakdown structure is an outcome oriented rankedclassification of work to be carried out by the project team, in reference to Project Management Body of Knowledge (PMBOK)(Siami-Irdemoosa, et al., 2010). The work breakdown structure illustrates the map of the project; showing the major steps and the sub steps to be followed up to the completion of the construction process.

2. Precedence Diagram Method
A precedence diagram method (PDM) is defined by the Code of Estimating Practice as a method of creating a reasonable network using nodes as a reference of the project activities by connecting them via lines that illustrate dependencies (The Chartered Institute of Building, 2009). The PDM is a technique that visually depicts the construction tasks and their scheduled program. The PDM is used to establish the critical path of construction

3. Critical Path
Critical path refers to the longest path, with the longest duration, in which an order of interdependent tasks must be undertaken before the project is declare complete. The critical path also illustrates the minimum period required for the project to be completed(R. & Norman, 2009).

4. Fast tracking
Fast tracking comprisesof overlapping tasks that were originally scheduled consecutively or optimizing the schedule in other areas. This may involve various solutions such as splitting longer tasks to smaller portions to compress more work into a shorter amount of time, minimizingdelays between tasks, diminishing the scope to eradicate less significant tasks or a blend of resource additions and planned activity variations(Bathhurst & Butler, 2010).

5. Crashing
Crashing refers to a program compression technique by incurring a higher cost for a minimised period of construction.

6. Float/slack
Float refers to the period of time that an activity may be delayed with no effects on the timely delivery of subsequent tasks and overall project completion date(M., 2002).

Work Breakdown Structure (WBS)
The figure below shows the work breakdown structure (WBS) for the M6 motorway project(See attached pdf file):

Work-Breakdown-Structure-WBS

Project Schedule
The figure below shows the project schedule for the M6 motorway project (See attached excel file):

Project schedule: M6 Motorway (Retaining wall)

Project schedule: M6 Motorway (Retaining wall)

 

ID

Name

Effort estimate
(days)

Planned start date

Planned end date

Resource

WBS 1

Pre-construction

 

 

 

 

M1.1

Site Set-up

10

19/10/2020

30/10/2020

Project management team

A0

Site preparation (compound)

10

19/10/2020

02/11/2020

Project management team, construction team

A1

Create an access road to the site area

3

20/10/2020

23/10/2020

construction team

A2

Install the boundary safety fence

5

21/10/2020

27/10/2020

construction team

A3

Install gates to the works site area

2

21/10/2020

23/10/2020

construction team

A4

Install welfare facilities e.gportaloos

2

26/10/2020

28/10/2020

construction team

B0

Site establish

10

26/10/2020

09/11/2020

Project management team, construction team

B1

Set up site offices

3

27/10/2020

30/10/2020

construction team

B2

Install services and utilities (gas, electricity & water)

5

29/10/2020

06/11/2020

construction team

B3

Install storage areas & containers

2

02/11/2020

04/11/2020

construction team

WBS 2

Construction

 

 

 

 

M1.2

Retaining wall

156

09/11/2020

15/01/2021

Project management team, construction team, consultants

C0

Excavation/Preparation

20

09/11/2020

04/12/2020

construction team

C1

Desk study to find out the services

3

09/11/2020

11/11/2020

Consultants

C2

CAT scan to locate the services

2

10/11/2020

12/11/2020

Consultants

C3

Setting out location of retaining wall

1

11/11/2020

11/11/2020

construction team

C4

Assess setting out

1

12/11/2020

12/11/2020

Consultants

C5

Excavation using plant

20

13/11/2020

04/11/2020

Project management team, construction team

D0

Base

25

18/11/2020

11/12/2020

construction team, consultants

D1-V1

Construct rebar cage

10

18/11/2020

02/12/2020

construction team, consultants

D3-V3

Install formwork

9

30/11/2020

11/12/2020

construction team

D4-V4

Check formwork

5

09/12/2020

15/12/2020

Consultants

D5-V5

Pour concrete

5

10/12/2020

17/12/2020

construction team

D6-V6

Testing (concrete tubes)

5

21/12/2020

25/12/2020

Consultants, project management

D7-V7

Strike formwork

5

01/01/2021

06/01/2021

construction team

E0

Stem

25

02/12/2020

05/01/2021

construction team, consultants

E1-W1

Tie stem rebar to base starter

4

02/12/2020

08/12/2020

construction team

E3-W3

Install formwork

5

04/12/2020

10/12/2020

construction team

E4-W4

Check formwork

3

08/12/2020

11/12/2020

Consultants

E5-W5

Pour concrete

5

09/12/2020

15/12/2020

construction team

F0

Joints

5

14/12/2020

18/12/2020

construction team, consultants

D2-W2

Install construction joint (per 10m)

5

14/12/2020

18/12/2020

construction team

M2-N2

Install expansion joint (per 50m)

5

14/12/2020

18/12/2020

construction team

X0

Brickwork façade

15

07/12/2020

25/12/2020

construction team

X1

Install brickwork 225mm

15

07/12/2020

25/12/2020

construction team

M1.3

Drainage

10

07/12/2020

18/12/2020

Project management team, construction team

G0

Drainage pipe

10

07/12/2020

18/12/2020

construction team

G6-W6

Lay granular drainage material down for pipe

5

07/12/2020

11/12/2020

construction team

G7-W7

Install 225 drainage pipe

5

14/12/2020

18/12/2020

construction team

M1.4

Backfill

20

17/12/2020

07/01/2021

construction team

Y0

Backfill of the area

20

17/12/2020

07/01/2021

construction team

Y1

Backfill the area with granular and granular drainage material

15

17/12/2020

05/01/2021

construction team

Y2

Place 225mm top soil

5

02/01/2021

09/01/2021

construction team

M1.5

Safety fence

5

03/01/2021

09/01/2021

construction team

Z0

Installation

5

03/01/2021

09/01/2021

construction team

Z1

Set out

2

03/01/2021

05/01/2021

Project management team, construction team

Z2

Construct 150mm post foundations

3

04/01/2021

09/01/2021

construction team

Z3

install 1200mm posts

3

04/01/2021

09/01/2021

construction team

Z4

Install rail

2

04/01/2021

06/01/2021

construction team

WBS 3

Post-construction

 

 

 

 

M1.6

Site closedown

20

07/01/2021

12/02/2021

Project management team, construction team, consultants

AA0

Handover

10

25/01/2021

12/02/2021

Project management team, construction team, consultants

AA1

Inspections with client

1

25/01/2021

25/01/2021

Project management team, construction team, consultants

AA2

Rectify any defects

8

26/01/2021

08/02/2021

Project management team, construction team, consultants

AA3

Official handover

1

12/02/2021

12/02/2021

Project management team, construction team, consultants

AB0

Site takedown

10

07/01/2021

21/01/2021

Project management team, construction team

AB1

Remove site offices & welfare facilities

2

04/02/2021

05/02/2021

construction team

AB2

Remove services & utilities

3

07/01/2021

12/01/2021

construction team

AB3

Remove storage areas &containers

2

07/01/2021

11/01/2021

construction team

AB4

Remove site boundary safety fence

10

07/01/2021

21/01/2021

construction team

AB5

Remove gates to compound

2

19/01/2021

21/01/2021

construction team

AB6

Demobilise staff

3

21/01/2021

08/02/2021

Project management team

 

 

 

 

 

 

Fig 2.Project Schedule

project schedule m6 motorway

Precedence manual program
(See attached excel file)

Part 2: Revisedproject schedules and programs

Gantt Chart

revised project schedules and programs

Precedence diagram
(See attached excel file)

Ways of speeding up the construction process to amend the program above
The following are measures that can be implemented to amend the project completion date:
1. Increase the number of skilled labourers when installing formwork, brickwork, and concreting works
2. Use modern efficient concrete mixers and pumps when concreting
3. Use more equipment when backfilling
4. Install drainage work during installation of the formwork
5. Install the formwork for the base, stems and joints simultaneously
6. Carry out the desk studies, CAT scans while carry out the site preparation and establishment activities
7. Do the installation of the safety fence while carrying out some site takedown activities

References
Bathhurst, P. & Butler, D., 2010. Building Cost Control Techniques and Economics. 3rd ed. Chicago: Heinemann.
Bogenstatter, U., 2003. Prediction and Optimization of Life-cycle costs. Washington: Build. Res. Information.
Chitkara, K., 2015. Construction Project Management. 3rd ed. New York: Tata McGraw-Hill Foundation.
Feely & Shrimpton, 2018. Cost Management and Reporting in Civil Engineering. 2nd ed. Liverpool: RICS Quantity Surveyors Division.
Flanagan & Tate, 2017. Cost Control in Building Design. 2nd ed. London: Blackwell Science.
Lester, A., 2007. Project Management, Planning and Control: Managing Engineering, construction and manufacturing projects to APM, PMI and BSI standards. 5th ed. London: Butterwoh-Heinamann.
M., P., 2002. A Value and Risk Management Approach to project development. London: New Civil Engineering International.

R., F. & Norman, G., 2009. Life Cycle Costing: Theory and Practice RICS. London: Surveyors Publications.
Sears, K., Sers, G. A. & Clough, R. H., 2010. Construction Project Management: A practical Guide to field consructon Management. 2nd ed. New York: John Wiley & Sons.
Siami-Irdemoosa, E., Dindarloo, S. & Sharifzadeh, 2010.
The Chartered Institute of Building, 2009. The Code of Estimating Practice. London: Rotal Minds Press.
Woodward, J. F., 2017. Construction Project Management: Getting it Right the first time. 3rd ed. Chicago: Telford Publishers.

NEXT SAMPLE

Related Samples

Question Bank

Looking for Your Assignment?

Search Assignment
Plagiarism free Assignment

FREE PARAPHRASING TOOL

PARAPHRASING TOOL
FREE PLAGIARISM CHECKER

FREE PLAGIARISM CHECKER

PLAGIARISM CHECKER
FREE PLAGIARISM CHECKER

FREE ESSAY TYPER TOOL

ESSAY TYPER
FREE WORD COUNT AND PAGE CALCULATOR

FREE WORD COUNT AND PAGE CALCULATOR

WORD PAGE COUNTER



AU ADDRESS
9/1 Pacific Highway, North Sydney, NSW, 2060
US ADDRESS
1 Vista Montana, San Jose, CA, 95134
ESCALATION EMAIL
support@totalassignment
help.com